City Council authorizes ongoing negotiations to protect ratepayers from Meta data center energy facility

Heriberto Perez, KVIA.

EL PASO, Texas (KVIA) -- Monday, the City of El Paso's City Council authorized the City Attorney, in consultation with the City Manager, to continue settlement negotiations and make a counteroffer for a "full hold harmless" for ratepayers from costs of the McCloud Generation facility.

During Monday’s City Council meeting, the City Attorney’s Office provided Council with an update on El Paso Electric's (EPE) application to construct the proposed 366-megawatt natural gas generation facility, which EPE proposes to use to serve Meta’s data center.

On September 23, two Administrative Law Judges (ALJ) issued a recommendation with the following after reviewing the evidence and arguments presented in the case:

  • The McCloud Generation facility may be approved only with protections intended to prevent EPE customers, other than Meta’s data center, from paying the plant’s construction and operating costs for the life of the facility.
  • Without those protections, the judges would recommend denying EPE’s application.
  • EPE could not simply shift McCloud’s construction and operating costs to other customers in the future. EPE would first have to return to state regulators and demonstrate that the costs should be allowed to be recovered from other customers.

According to City officials, the judges also found that EPE did not adequately consider alternatives or demonstrate that the proposed McCloud Generation facility was the most cost-effective option.

The ALJ recommendation is not a final decision; the five Public Utility Commission of Texas (PUCT) commissioners will make the final decision on whether to accept, change, or reject the recommendation. The PUCT is expected to issue a final order by December 7, 2026.

The City says that in addition to protecting ratepayers from McCloud’s construction and operating costs, a “full hold harmless” would protect customers from other financial impacts, including the potential loss of revenue credits from EPE’s off-system power sales.

Article Topic Follows: News

Jump to comments ↓

Armando Ramirez

BE PART OF THE CONVERSATION

KVIA ABC 7 is committed to providing a forum for civil and constructive conversation.

Please keep your comments respectful and relevant. You can review our Community Guidelines by clicking here

If you would like to share a story idea, please submit it here.