Road closures in El Paso County for the week of Nov. 7 to Nov. 11
EL PASO, Texas -- From west to east El Paso there's a construction project in almost every part of the Borderland. Here's a complete list of TxDOT's road closures for the week of November 7 to November 11.
El Paso District west area project, maintenance closures
Transmountain Project
Monday, November 7 through Thursday, November 10
9 a.m. to 4 p.m.
- Loop 375 (Transmountain) east and westbound between US-54 and Tom Mays State Park alternate lane closures including shoulders. Bike lane closed.
Crews will be working on median drilling cable post foundations and installation.
Antonio Street Rehabilitation Roadway Project
Continuous until further notice.
- FM 1905 east and westbound alternate lane closures.
Crews will be working on demolition and reconstruction improvements.
Doniphan Raised Median Project (SH-20)
Continuous until further notice.
- Doniphan east and westbound between Thorn and Redd left lane closed.
- Doniphan east and westbound between Coates and Artcraft left lane closed.
Crews will be working on median improvements.
Guardrail Repair Project
Monday, November 7
9 a.m. to 4 p.m.
- Gateway North between Cassidy and Fred Wilson two left lanes closed.
- Loop 375 (Border Highway) westbound between Ramp R and Paisano right lane closed.
Tuesday, November 8
9 a.m. to 12 p.m.
- Gateway South at Pershing on-ramp complete closure.
Tuesday, November 8
Night, 9 p.m. to 4 a.m.
- Wyoming eastbound at Kansas on-ramp complete closure.
Wednesday, November 9
Night, 9 p.m. to 4 a.m.
- I-10 westbound between Ange and Mesa two right lanes and Mesa exit ramp closed.
Miscellaneous Concrete
Wednesday, November 9 and Thursday, November 10
9 a.m. to 4 p.m.
- I-10 westbound between Asarco Bridge and Executive right lane closed.
Crews will be working on riprap.
Spall Repair Project
Monday, November 7
Night, 9 p.m. to 5 a.m.
- I-10 eastbound between Ramp 18B (Porfirio Diaz) and Schuster alternate lane closures.
Crews will be working on spall repair.
Tuesday, November 8
Night, 9 p.m. to 5 a.m.
- I-10 eastbound between Geronimo and Airway alternate lane closures.
Crews will be working on spall repair.
Wednesday, November 9
Night, 9 p.m. to 5 a.m.
- Gateway North between Fred Wilson and Broaddus alternate lane closures.
Crews will be working on spall repair.
Maintenance
Monday, November 7 through Thursday, November 10
9 a.m. to 3 p.m.
- I-10 eastbound at Cotton entrance ramp closed.
Crews will be working on bridge joints.
- US-54 southbound between Paisano and Loop 375 (Border Highway) alternate lane closures.
- Paisano entrance ramp to US-54 southbound closed.
Crews will be working on potholes.
- Diana westbound between Kenworthy and Gateway North left lane closed.
Crews will be working on curbs.
- Loop 375 (Border Highway) between Santa Fe and Campbell right lane closed.
Crews will be installing signs.
- US-54 northbound at Hondo Pass exit closed.
- Gateway North between Moonlight and Hondo Pass left lane closed.
Crews will be installing delineators.
El Paso District east area project, maintenance closures
Loop 375 Widening Project
Sunday, November 6 through Thursday, November 10
Nightly, 9:00 p.m. to 5:00 a.m.
- Americas Highway (Loop 375) northbound main lanes closure from Zaragoza POE to North Loop Drive
Crews will be doing demolition
Sunday, November 6 through Monday, November 7
Nightly, 9:00 p.m. until 5:00 a.m.
- Pan American intersection at Americas Avenue complete closure
Crews will be working on bridge demolition
Sunday, November 6 through Thursday, November 10
Nightly, 9:00 p.m. until 5:00 a.m.
- North Loop intersection at Americas Avenue complete closure
Crews will be working on bridge demolition
Monday, November 7 through Thursday, November 10
Daily, 9:00 a.m. to 4:00 p.m.
- Americas Avenue southbound left lane at Bob Hope and entrance ramp closure
Crews will be working on utilities
- Americas Avenue northbound left lane from Rojas entrance ramp to Bob Hope Drive
Crews will be removing retaining wall
Tuesday, November 8
9:00 a.m. until 4:00 p.m.
- Americas Highway (Loop 375) southbound connector right shoulder closure from I-10 to North Loop Drive
Crews will be working on utilities
Continuous closures until further notice
- S Americas Avenue northbound Pan American exit ramp closed
- S Americas Avenue at Pan American Drive turnarounds in both directions will be closed
- S Americas Avenue at Socorro Road turnarounds in both directions will be closed
- S Americas Avenue at North Loop Drive turnarounds in both directions will be closed
- Loop 375 southbound to northbound truck turnaround at S Americas will be closed
- S Americas Avenue northbound to southbound turnaround at Alameda Avenue will be closed
Crews will be widening LP 375 main lane bridge structures
Zaragoza Mill and Inlay Project
Sunday, November 6 through Thursday, November 10
Nightly, from 9 p.m. until 5 a.m. (overnight)
Monday, November 7 through Friday, November 11
Daily, from 9:00 a.m. until 4:00 p.m.
- Zaragoza Road (FM 659) north and southbound alternating right and left lane closures between North Loop Drive and Gateway West Boulevard
- Traffic will be reduced to one lane in work areas
Crews will be removing and installing illumination poles
Sunday, November 6 through Thursday, November 10
Nightly, from 8:30 p.m. until 5 a.m. (overnight)
Monday, November 7 through Friday, November 11
Daily, from 9 a.m. until 4 p.m.
- Zaragoza Road (FM 659) north and southbound alternating right and left lane closures between George Dieter Drive and Saul Kleinfeld Drive
- Traffic will be reduced to one lane in work areas
Crews will be constructing center medians and striping
Sunday, November 6 through Thursday, November 10
Nightly, from 7 p.m. until 5 a.m. (overnight)
Monday, November 7 through Friday, November 11
Daily, 9 a.m. until 4 p.m.
- Zaragoza Road (FM 659) north and southbound right lane closure between Edgemere Boulevard and Montana Avenue (US 62/180)
- Traffic will be reduced to one lane in work areas
Crews will be constructing illumination conduit and foundations
Sunday, November 6 through Thursday, November 10
Nightly, from 8:30 p.m. until 5 a.m. (overnight)
- Zaragoza Road (FM 659) north and southbound alternating right and left lane closures between Sun Fire Boulevard and Montana Avenue (US 62/180)
- Traffic will be reduced to one lane in work areas
Monday, November 7 through Friday, November 11
Daily, from 9:00 a.m. until 4:00 p.m.
- Zaragoza Road (FM 659) north and southbound left lane closure between Sun Fire Boulevard and Montana Avenue (US 62/180)
- Traffic will be reduced to one lane in work areas
Crews will be constructing center medians, pavement, and striping
Construction of Safety Lighting Project
Monday, November 7 through Friday, November 11
Daily, from 8 a.m. until 4 p.m.
- I-10 westbound inside left shoulder closure at Darrington Road and Clint exit ramp
Monday, November 7, and Tuesday November 8
Daily, from 8 a.m. until 4:00 p.m.
- Gateway East Boulevard at Darrington Road and Clint exit ramp eastbound right lane closure on frontage road
Crews will be drilling for high mast illumination drill shaft.
Passing Lanes Project
Monday, November 7 through Friday, November 11
Daily, from 7 a.m. until 5 p.m.
- US 62/180 MM 78 to 94 east and westbound right and left lane and shoulder closure
Crews will be working on level up locations on non-widening sections.
Continuous until further notice
- US 62/180 (FM1111) intersection will be closed for demolition and reconstruction
Resurfacing Frontage Road
Sunday, November 6
7:00 p.m. until 6:00 a.m. (overnight)
Monday, November 7 through Wednesday November 9
Nightly, 8:00 p.m. until 6:00 a.m.
- Americas Avenue southbound frontage road alternating lane closure from Pine Springs Drive to I-10
Crews will be working on frontage road 2” planning
Wednesday, November 9 through Thursday November 10
Nightly, 8:00 p.m. until 6:00 a.m.
- Americas Avenue southbound frontage road right lane closure from I-10 to North Loop Drive (FM76)
Crews will be working on frontage road 2” planning
Sunday, November 6 through Wednesday, November 9
Nightly, 7:00 p.m. until 6:00 a.m.
- Rojas intersection at Americas Avenue complete closure
Crews will be working on frontage road 2” planning
Landscaping Project
Monday, November 7 through Friday, November 11
Daily, from 7 a.m. until 4 p.m.
- I-10 to Joe Battle Four Clovers and Americas Interchange east and westbound right shoulder closure
Daily, from 9 a.m. until 4 p.m.
- I-10 east and westbound alternating entrance and exit ramp closures at Eastlake Boulevard
Crews will install aggregates for landscape improvements
Horizon/Alameda Raised Median Project
Monday, November 7 through Friday, November 11
Daily, from 7 a.m. until 5 p.m.
- Horizon Boulevard (FM1281) north and southbound left lanes closure from Doy Drive to Ellsworth Drive
- Horizon Boulevard (FM1281) alternating right lane and shoulder closure from Kenazo Drive to Crocker Drive
- Traffic will be reduced to one lane
Crews will be installing crash cushion wing assembly and pouring concrete curb
Monday, November 7 through Friday, November 11
Daily, from 7 a.m. until 5 p.m.
- Alameda Avenue (SH-20) east and westbound alternating right lane closure at George Orr Road intersection
Crews will be pouring concrete sidewalk
I-10 Widening East
Monday, November 7 through Saturday, November 12
Daily, from 8 a.m. until 4 p.m.
- I-10 eastbound right main lane and shoulder closures between Horizon Boulevard and Eastlake Boulevard
Crews will be working on pedestrian fence and rock wall
Continuous until further notice
- I-10 eastbound and westbound left shoulder closures between Horizon Boulevard and Eastlake Boulevard
Crews will be preparing form for concrete traffic barrier and installing high mast illumination poles and various other projects
Tornillo Bridge Reconstruction
Monday, November 7 through Friday November 11
Daily from 7 a.m. until 5:00 p.m.
- I-10 east and westbound alternating right and left lane closure between Tornillo MM 55 and MM 57
Crews will be working on caps
Continuous until further notice
Tornillo Bridge (FM 3380) over I-10 will be closed for demolition and reconstruction
Metal Beam Guard Fence Replacement Project
Monday, November 7 through Friday November 11
Daily, from 7 a.m. until 4 p.m.
- I-10 east and westbound alternating lane closures between Tornillo MM 57 and MM 59
Crews will be removing and replacing Metal Beam Guard fence
Diamond Grinding & NGCS Project
Monday, November 7 through Friday November 11
Daily, from 7 a.m. until 4 p.m.
- I-10 westbound alternating lane closure between MM 62 and MM 71
Crews will be performing conventional grinding and Next Generation Concrete Surface Grinding
CONTINUOUS CLOSURES
Purple Heart Loop 375 Widening
Continuous until further notice
- Purple Heart Highway north and southbound shoulder closures from Montana Avenue to Spur 601
Crews will be constructing north and southbound frontage road, placing RCP, and widening the Tank Trail Bridge.
Median Concrete Barrier Project
Continuous until further notice
- Montana Avenue (US 62/180) east and westbound complete left lane closure between RM 124 and RM 126 (Guadalupe Peak)
- Traffic will be reduced to one lane in work areas
Closure is necessary for installation of median concrete barrier
RM 652 Full Depth Rehabilitation Project
Continuous until further notice
- RM 652 east and westbound alternating lane closure 8.36 miles east of FM 3541 to Reeves County Line
- Continuous two-way traffic, one-lane work zone requiring traffic to be alternating onto one lane and controlled by Temporary Traffic Signals with a 13-foot lane width restriction
- Carlsbad access road closed
Closure is necessary for the construction of new roadway consisting of full depth rehabilitation
RM 652 Widening Project
Continuous until further notice
- RM 652 continuous alternating east and westbound left lane closures between RM 1165 and 0.91 mile west of FM 3541
- Continuous two-way traffic, one-lane work zone requiring traffic to be alternating onto one lane and controlled by Temporary Traffic Signals with 14-foot lane width restriction
Closure is necessary for the construction of new roadway consisting of full depth rehabilitation