I-10 Widening West
Monday, February 13
9 p.m. to 5 a.m.
- Westbound I-10 will be closed to all traffic between Vinton Road and Anthony, Texas.
- DETOUR: Take Exit 2 (Spur 37/Vinton Road/Westway Drive), continue on North Desert Boulevard, re-enter I-10 past Anthony, Texas.
Crews will be placing concrete safety barriers.
Tuesday, February 14
9 p.m. to 5 a.m.
- North Desert Boulevard will be closed to all traffic between the Vinton Road onramp and Anthony, Texas.
- Westbound Exit 0 (FM 1905/Anthony) will be closed to all traffic.
- DETOUR: Turn left on Spur 37 (Vinton Road/Westway Drive), turn right on SH 20 (Doniphan Drive), turn right on Spur 6 (Wildcat Drive), and turn right on FM 1905 (Antonio Street).
Crews will be placing concrete safety barriers.
Wednesday, February 15
9 p.m. to 5 a.m.
- Eastbound I-10 will be closed to all traffic between Anthony, Texas, and Vinton Road.
- Take Exit 0 (FM 1905/Anthony), continue on South Desert Boulevard, and re-enter I-10 past Vinton Road.
Crews will be placing concrete safety barriers.
Thursday, February 16
9 p.m. to 5 a.m.
- South Desert Boulevard will be closed to all traffic between Anthony, Texas, and Vinton Road.
- DETOUR: Enter eastbound I-10 at Anthony and take Exit 2 (Spur 37/Vinton Road/Westway Drive).
Crews will be placing concrete safety barriers.
I-10 Connect
Monday, February 13, through Friday, February 17
8 a.m. to 4 p.m.
- A closure of the right two lanes of I-110 southbound, from the pedestrian bridge to E-Access, will be in place.
Crews will be performing work on a sound wall.
Monday, February 13, through Friday, February 17
8 a.m. to 4 p.m.
- A closure of Gateway East, from the Copia ramp to the Raynolds Street exit ramp, will be in place. DETOUR: Traffic from Gateway East should proceed to I-10 eastbound and exit at the Raynolds exit ramp. Lincoln Center will have access through Durazno Avenue.
Crews will be performing painting work.
Bridge Joint Cleaning
Sunday, February 12
8 a.m. to 4 p.m.
- US-54 southbound between Cassidy and Trowbridge alternate lane closures.
Crews will be cleaning and sealing bridge joints.
Monday, February 13
9 a.m. to 4 p.m.
- North Oregon between Wyoming and Yandell alternate lane closures.
Crews will be cleaning and sealing bridge joints.
Tuesday, February 14
9 a.m. to 4 p.m.
- North Mesa between Yandell and Wyoming alternate lane closures.
Crews will be cleaning and sealing bridge joints.
Wednesday, February 15
9 a.m. to 4 p.m.
- North Kansas between East Missouri and Yandell alternate lane closures.
Crews will be cleaning and sealing bridge joints.
Thursday, February 16 and Friday, February 17
9 a.m. to 4 p.m.
- I-0 eastbound between Schuster and Executive overpass alternate lane closures.
Crews will be cleaning and sealing bridge joints.
Guardrail Repair Project
Monday, February 13
9 a.m. to 4 p.m.
- SH-20 (Doniphan) northbound between Coates and Montoya right lane closed.
Tuesday, February 14
9 a.m. to 4 p.m.
- Loop 375 (Transmountain) eastbound between three miles east of Main Gap and Wilderness Museum right lane closed.
Wednesday, February 15
9 a.m. to 4 p.m.
- I-10 eastbound between Porfirio Diaz and Santa Fe right lane closed.
Thursday, February 16
9 a.m. to 4 p.m.
- I-10 eastbound between Schuster and Porfirio Diaz right lane closed.
Friday, February 17
9 a.m. to 4 p.m.
- CD lanes westbound between Resler and Mesa right lane closed.
Miscellaneous Concrete Repair
Monday, February 13 and Tuesday, February 14
9 a.m. to 4 p.m.
- US-54 southbound between Cassidy and Pershing left lane closed.
- US-54 northbound between Pershing and Cassidy left lane closed.
Crews will be repairing concrete barriers.
Wednesday, February 15 and Thursday, February 16
9 a.m. to 4 p.m.
- CD lanes westbound between Resler and Mesa right lane closed.
Crews will be repairing concrete barriers.
Friday, February 17
9 a.m. to 4 p.m.
- US-54 southbound between Cassidy and Pershing left lane closed.
- US-54 northbound between Pershing and Cassidy left lane closed.
Crews will be repairing concrete barriers.
Maintenance
Monday, February 13 through Friday, February 17
9 a.m. to 3 p.m.
- US-54 southbound between Paisano and Loop 375 (Border Highway) alternate lane closures.
- Paisano on-ramp to US-54 southbound closed.
- US-54 north and southbound between Hondo Pass and Dyer alternate lane closures.
- US-54 north and southbound between Hercules and Dyer alternate lane closures.
Crews will be repairing crack seal on bridge deck.
- US-54 southbound between Altura and Montana right lane closed.
- US-54 southbound Montana exit ramp closed.
- US-54 northbound Trowbridge exit ramp closed.
- US-54 north and southbound between Dyer and Hercules alternate lane closures.
- Dyer on-ramp to US-54 closed.
Crews will be repairing bridge.
- Spur 601 eastbound between Airport and Global Reach right lane closed.
- Spur 601 eastbound Global Reach exit ramp closed.
Crews will be working on shoulder.
Loop 375 Widening Project
Monday, February 13 through Thursday, February 16
Nightly 9:00 p.m. until 5:00 a.m.
- Americas Highway (Loop 375) southbound main lane closure from Pan American Exit Ramp to Zaragoza Entrance Ramp
- Zaragoza Port of Entry Underpass
Crews will be doing bridge demo
I-10 Widening East
Sunday, February 12 through Thursday, February 16
Nightly, from 9:00 p.m. until 5:00 a.m.
- I-10 Westbound alternating right lane closure between Eastlake Overpass to Horizon Overpass
Crews will be working on striping
Monday, February 13 through Friday, February 17
Daily, from 9:00 a.m. until 4:00 p.m.
- Gateway East and West alternating right lane closure between Eastlake Overpass to Horizon Overpass
Crews will be pouring high mast aprons and metal panels for pedestrian fence