Road closures in El Paso County, Las Cruces Wednesday, June 28
EL PASO, Texas (KVIA) -- Here is a list of road closures scheduled for Wednesday, June 28 for El Paso County and the City of Las Cruces.
For updates in El Paso, click here. For a look at more information from TxDOT, click here. For updates in Las Cruces, click here.
Transmountain Project
Monday, June 26 through Friday, June 30
9 a.m.to 4 p.m.
- Loop 375 (Transmountain) east and westbound between US-54 and Tom Mays State Park alternate lane closures. Bike lane closed.
Crews will be performing general clean-up and cable barrier installation.
Doniphan Raised Median Project (SH-20)
Continuous until further notice.
- 6018 Doniphan northbound between Montoya and Artcraft right lane closed.
Crews will be working on median improvements.
US-54 Realign Intersection at Stan Roberts and State Line Road Project
Monday, June 26 through Friday, June 30
- US 54 north and southbound at Stan Roberts shoulders closed.
Crews will be realigning the intersection.
Green Ribbon Project
Monday, June 26 through Friday, June 30
9 a.m. to 4 p.m.
- Montana east and westbound between Killarney and Airway left lane closed.
- Doniphan east and westbound between Thorn and Borderland left lane closed.
Crews will be installing new landscape.
Guardrail Repair Project
Wednesday, June 28
9 a.m. to 4 p.m.
- Loop 375 (Transmountain) westbound between Border Museum and Main Gap right lane closed.
Maintenance
Monday, June 26 through Friday, June 30
9 a.m. to 3 p.m.
- I-10 eastbound at Schuster alternate lane closures.
- I-10 east and westbound between Trowbridge and Buffalo Soldier alternate lane closures.
Crews will be repairing crack seal on bridge deck.
- Loop 375 (Transmountain) east and westbound between MM 18 and MM 13 at the Main Gap right lane closed.
Crews will be working on shoulder.
- I-10 east and westbound between Trowbridge and McRae alternating lane closures.
Crews will be cleaning turnarounds and intersections.
- Loop 375 (Border Highway) east and westbound between Zaragoza and Fonseca alternating lane closures.
Crews will be cleaning turnarounds and intersections.
- Yandell entrance ramp to US-54 South closed.
- Woodrow Bean east and westbound at the Bomarc underpass closed.
Crews will be cleaning.
Please follow the detour signs in place on all projects. All work is dependent upon weather conditions.
LAS CRUCES
There will be shoulder work on Robert Larson Boulevard, between Crawford Boulevard to Rea Boulevard, and along Mountain Vista Parkway from Wednesday June 28, 2023, to Friday July 7, 2023.
No work will be done July 4, 2023, due to the Fourth of July holiday.
Conterra Networks will be working as part of a wire utility permit.
The shoulder work will not impact the RoadRUNNER Transit routes. This work is being done at Las Cruces Innovation and Industrial Park, in City Council District 4.